August 18, 2018 On August 18th, the PEACE TRAIN ran in Kingston. Brian Van Kirk, was engineer, Tony Bocchino was conductor, Karl Wick was brakeman, Joe Wolff and Martin Elbrecht were flagmen, with Ken Harris flagman trainee. Marcia Roosa was in the ticket booth with Peter Fluchere. Joe Wolff also worked on upgrading the electrical in the caboose. August 19, 2018 On August 19th, we had the 2nd rules class of the year. 14 CMRR members and 4 of our employees passed the test. Route 209 Crossing nears completion: http://photos.greatrails.net/s/?p=245532 http://photos.greatrails.net/s/?p=245533 Ernie Hunt Staff/Volunteer Coordinator CMRR |
Author: | traincrew [ Wed Aug 22, 2018 2:24 pm ] |
Post subject: | Re: Catskill Mountain Railroad (CMRR) Discussion - 2018 |
Everything looks great. Don't know how you guys do it. |
Author: | eehiv [ Wed Aug 22, 2018 3:11 pm ] |
Post subject: | Re: Catskill Mountain Railroad (CMRR) Discussion - 2018 |
I would love to take credit for this, but this project is being done by WJ Riegel and is funded directly by NY State. EH |
Author: | eehiv [ Sun Aug 26, 2018 11:57 pm ] |
Post subject: | CMRR Work Report - 8/20 to 8/25 |
August 20, 2018 Ryan Lennox weed-wacked the Phoenicia Yard. August 23, 2018 On August 23 we ran a charter. Bryan Van Kirk was Engineer, Walt Otto was conductor, Fred Ehren was brakeman, Ryan Lennox and Ken Harris were flaggers. August 25, 2018 On August 25th, the PEACE TRAIN ran in Kingston. Brian Van Kirk, was engineer, Tony Bocchino was conductor, Tom Whyte was brakeman, and Martin Elbrecht was flagman. Joe Wolff worked on the caboose. Marcia Roosa was in the ticket booth with Peter Fluchere. Additionally, the work on the 209 crossing is nearly complete. Below is a photo from Friday August 24th: http://photos.greatrails.net/s/?p=245591 Ernie Hunt Staff/Volunteer Coordinator CMRR |
Author: | eehiv [ Fri Aug 31, 2018 9:57 am ] |
Post subject: | CMRR Dog Crossing Project Complete |
The CMRR completed its rebuild of the "Dog Crossing" yesterday and of about 500 feet of track east and west of the crossing yesterday: http://photos.greatrails.net/s/?p=245682 http://photos.greatrails.net/s/?p=245683 http://photos.greatrails.net/s/?p=245684 Many thanks to all who worked on this project this year. Ernie Hunt President CMRR |
Author: | joe6167 [ Fri Aug 31, 2018 11:28 am ] |
Post subject: | Re: Catskill Mountain Railroad (CMRR) Discussion - 2018 |
Is MP 6.55 the end of track or do you have track beyond that suitable for excursion service? |
Author: | eehiv [ Fri Aug 31, 2018 12:00 pm ] |
Post subject: | Re: Catskill Mountain Railroad (CMRR) Discussion - 2018 |
We extended the EOT from MP 6.45 to MP 6.57 from this project which involved complete track replacement. After this its tie insertions mostly and we plan to continue work this fall going west. EH |
Author: | eehiv [ Wed Sep 05, 2018 11:11 pm ] |
Post subject: | CMRR Work Report - 8/26 to 9/4 |
August 26-31, 2018 Earl Pardini, John Marino, Bryan Van Kirk and Vince Guido completed the Dog Crossing project. September 1, 2018 On September 1, the GREAT TRAIN ROBBERY ran in Kingston. Earl Pardini and John Marino were engineers, Tony Bocchino was conductor, John Marino and Ed Winstanley were brakeman, and Martin Elbrecht, Ken Harris and Russell Hallock were flagmen. Marcia Roosa was in the ticket booth with Peter Fluchere. The train went all the way to the Dog Crossing for the first time. We also crossed the new 209 crossing for the first time. September 4, 2018 Earl Pardini, Todd Syska, Russ Hallock and Ryan Lennox opened up the track from the Dog Crossing to MP 8.33. Ernie Hunt Staff/Volunteer Coordinator CMRR |
Author: | eehiv [ Tue Sep 11, 2018 12:59 am ] |
Post subject: | CMRR Work Report - 9/4, 9/8 |
September 4, 2018 Earl Pardini, Todd Syska, Ryan Lennox and Russ Hallock cut trees from the ROW from MP 28a at Stoney Hollow to the Dog Crossing. The tracks are now clear and ready for our expansion west. September 8, 2018 Earl Pardini led a crew consisting of John Marino, Raphel DeMeglio, Russ Hallocn and Bruce Tuchman who inserted and spiked 25 ties west of the Dog Crossing. http://photos.greatrails.net/s/?p=245835 http://photos.greatrails.net/s/?p=245836 http://photos.greatrails.net/s/?p=245837 http://photos.greatrails.net/s/?p=245838 http://photos.greatrails.net/s/?p=245839 In Kingston, Ernie Klopping and Martin Elbrecht worked on the 2949 generator, and Joe Wolff worked on a new light for the rear of the caboose. Vince Guido continues work on the Section House: http://photos.greatrails.net/s/?p=245833 Ernie Hunt Staff/Volunteer Coordinator CMRR |
Author: | eehiv [ Mon Sep 17, 2018 10:48 pm ] |
Post subject: | CMRR Work Report - 9/13 to 9/15 |
September 13, 2018 Earl Pardini, John Marino and Bryan Van Kirk ballasted and tamped newly reconstructed track west of the Dog Crossing. September 14, 2018 Earl Pardini Bryan Van Kirk, Ryan Lennox and Russell Hallock moved some equipment up the line to MP 7.5 and moved other equipment to Hurley Mountain Road. Art Vogel assisted with the crane. September 15, 2018 Earl Pardini, John Marino, Raphael DeMeglio and Ryan Lennox removed OTM west of Hurley Mountain Road in preparation for tie replacements. Ernie Hunt Staff/Volunteer Coordinator CMRR |
Author: | eehiv [ Thu Sep 20, 2018 9:34 am ] |
Post subject: | Another Vote to Remove U&D Tracks |
Thursday (today) the Ulster County Legislature votes on Resolution 362 which removes the rails from Chandler Drive to Downs Street, permanently severing our connection to CSX: https://ulstercountyny.gov/sites/defaul ... -%2018.pdf Although the resolution was defeated in the Energy andEnvironment Committee, a "petition to discharge" was sponsored by Ken Ronk, the UC Legislature Chairman, and it got enough votes to override the committee and move the resolution to the floor for a vote Thursday night. See this Daily Freeman article: http://www.dailyfreeman.com/general-new ... n-kingston The CMRR has written directly to the legislature to ask them topostpone this vote until the UC TRAC Committee can review this resolution as well as a counter-proposal that the CMRR has recommended. This proposal is that the CMRR will constructs the police, EMT and maintenance access road proposed in the resolution on top of the tracks, but leaves the rails in place for now, splitting the cost with the County. The letter and proposal can be viewed here: https://www.catskillmountainrailroad.co ... 1918-2.pdf We are hoping that they will delay the vote until our proposal can be fully reviewed. EH |
Author: | eehiv [ Sat Sep 22, 2018 1:21 am ] |
Post subject: | Re: Catskill Mountain Railroad (CMRR) Discussion - 2018 |
More tracks are coming up: https://www.dailyfreeman.com/news/local ... 470e9.html This will permanently sever the CMRR from the national rail network. EH |
Author: | jayrod [ Sat Sep 22, 2018 8:38 am ] |
Post subject: | Re: Catskill Mountain Railroad (CMRR) Discussion - 2018 |
Hmmm... Pulling up the track isn't dealing with the homeless problem. Paving the rail bed will make it more convenient for them. How many people are there in Kingston midtown that don't have vehicles and will walk that far to the grocery store? I'd guess not that many. How does that justify the expense? I'd be a bit miffed if I was a tax payer in that county over all the money being spent on this entire "problem". My two cents from the nose-bleed seats.... |
Author: | bigjim4life [ Sun Sep 23, 2018 10:55 am ] |
Post subject: | Re: Catskill Mountain Railroad (CMRR) Discussion - 2018 |
I still say it’s time to pack up and leave - the county doesn’t want you there and will only continue to fight until you’re completely gone. Sad but true. |
Author: | eehiv [ Mon Sep 24, 2018 1:23 pm ] |
Post subject: | CMRR Work Report - September 17 to 22 |
September 17 to 22 Last week the crew inserted nearly 500 ties from Hurley Mountain road to the Dog Crossing, 80 west of the Dog Crossing, and another 15 west of C9. All the ties are spiked except for 75 between the North Pole and our former end of track at MP 6.45 and 80 west of the Dog crossing up to MP 6.67. They also laid out 325 ties for insertion between MP 6.67 and 6.85 in October. http://photos.greatrails.net/s/?p=246073 http://photos.greatrails.net/s/?p=246074 http://photos.greatrails.net/s/?p=246075 The CMRR crew consisted of Earl Pardini, Tom Whyte, Bryan Van Kirk, Ryan Lennox, Sam Cogan, Raphael DeMeglio, Ken Harris, Sean Newton, Russ Hallock, and newcomer Dylan Iurato. Many thanks to all! Ernie Hunt Staff/Volunteer Coordinator CMRR |